1031 E. Monument street - 3,500 sq ft
From Rectory to Cooperative Housing

IMG_20190508_085054278.jpg
IMG_20190508_085059924.jpg
Construction timeline

2020 - 2021 : Acquire Rectory, preliminary design
2021 - 2022 : Fundraise for renovation of rectory
2021 -           : Hire Adams Design Group (MBE) for concept design and
                       construction documents
2022 - 2023 : Apply for permit from the City of Ba
ltimore
2023 -           : Hire Bristol Community Construction (MBE) for renovation of rectory
2023             : Groundbreaking
2023 - 2024 : Demolition and renovation of rectory-images
2024 -          : Full occupancy of 7 units of Cooperative Housing


 

View Renovation of 1025 Monument into Intentional Cooperative Housing

           Sept 2023 Groundbreaking                        Sept 2023 First Floor   Unit 1                     Sept Basement ADA Unit                Sept 2023 Basement Dining area   

IMG_5105.jpeg
IMG_5103.jpeg
IMG_5102.jpeg

         Sept 2023 Basement Kitchen                Sept  2023 Second Floor   Unit 3            Sept 2023 Basement Common area         Oct 2023 First Floor Unit 1   

IMG_5104.jpeg
IMG_5144.jpeg
IMG_5106.jpeg

         Oct 2023 Second Floor Unit 3                                   Oct 2023 Basement ADA unit/bathroom                           Oct 2023 Second Floor bathroom

IMG_5142.jpeg
IMG_5143.jpeg
IMG_5587.jpeg
IMG_5588.jpeg

  Oct 2023 Second floor Bathroom               Oct 2023 Second floor bathroom                 Oct 2023 First floor Unit 2                     Oct 2023 First Floor Unit 1 and 2

IMG_5780.jpeg
IMG_5778.jpeg

        Nov 2023 Second Floor Unit 6                 Nov 2023 First Floor Unit 1        Nov 2023 First floor Unit 2, Bathroom         Dec 2023 First floor Unit 1              

IMG_6372.jpeg

             Dec 2023 First Floor Unit 2                Dec 2023 Second Floor Unit 6             Dec 2023 First floor Common Area                Jan 2024 Basement ADA unit

IMG_6368.jpeg

          Jan 2024 Second Floor Unit 5                         

1025 E. Monument street - 12,500 sq ft
From church to community hub

DSC_0451(1).JPG
Construction timeline

2020 - 2021 : Acquire Church, preliminary design
2022 - 2024 : Fundraise for renovation of church
2023 -           : Recruit and Hire SGodley Architects (MBE) for schematic design and
                       construction documents
2023 - 2024 : Apply for permit from the City of Baltimore
2023 -          : Hire Construction Company (MBE) for renovation of rectory
2024 -          : Demolition and renovation of church
2025 -          : Full occupancy of Community Hub (Wellness Center,
                      Day Care, Event space, Commercial kitchen, Organizing
                      School, Community meeting space, Shared office space,
                      Retail pop-up space)


 